|
|
Minutes of the meeting of the University Council held
on Friday 19 March 2010.
Members:
Sir Bryan Carsberg
(Chair); Dr Memis Acar; Dr Jo
Aldridge (ab); Dr Anja Baumhoff; John Blackwell; Penny Coates (ab); Dr Sandie Dann;
Arthur Deakin (ab); Brian Dent (ab); Gifty Edila; Sir John Gains; Professor
Neil Halliwell; Rob Hulme; Sir John Jennings; Jamie Morgado; Jim Murphy; Jim
Mutton; Terry Neale; Professor Ric Parker (ab); Professor Richard Parry-Jones
(ab); Professor Shirley Pearce; Simon Proffitt; Professor Ian Reid; Mark
Sismey-Durrant (ab); Jackie Strong; Nigel Tamplin; Philip Wilkinson-Blake; Alan
A Woods; Dr Dominic Wring.
In attendance:
Rob Allen; Professor Morag Bell; Dr Sophie Crouchman; Professor Phill Dickens; Chris Dunbobbin; Professor Chris Linton; Sir Charles McCullough; Dr Jennifer Nutkins; Will Spinks; Caroline Walker; Jon Walker.
Apologies
for absence were received from:
Dr Jo
Aldridge; Penny Coates; Arthur Deakin; Brian Dent; Professor Ric Parker;
Professor Richard Parry-Jones; Mark Sismey-Durrant;
The Chairman welcomed the University Visitor, Sir Charles McCullough, to the meeting.
Item 16. was unstarred.
Minutes of the Meeting of Council held on 27 November 2009 (COUN09-M7) were CONFIRMED.
COUN10-P1 & COUN10-P2
04.1 Further
to minute 09/96.4, Council RECEIVED a summary of background information
relating to the University’s purchase of the Quality Hotel (now The Link
hotel) and APPROVED the loan facility with Lloyds TSB. The following
points were noted:
(i) The
purchase would not affect the University’s capital programme.
(ii) The
interest rate on the loan was at a competitive level.
(iii) The
hotel had been purchased in the University’s name, and would be leased to
imago Ltd, in return for a rent. Gift aid of profits would benefit the
University. Under this arrangement, the University’s charitable status
would be unaffected.
04.2 Council
NOTED that, on 9 December 2009, the Privy Council had approved changes
to the Charter and Statutes.
COUN10-P3
Council RECEIVED an update on the University
Strategy and Implementation Plans following the Executive Leadership Team Away
Day.
It was noted in discussion that initial
proposals on the future structure and organisation of the University had been
considered by Senate on 27 January 2010. A Project Management Board (PMB),
chaired by the Dean of Science, had subsequently been established by Operations
Committee with the aim of recommending an action plan to complete the change to
a larger cost centre (School) operation. The proposed reorganisation was a
sensitive issue, and the PMB would consult widely before producing
recommendations for consideration by Senate and Council in June/July 2010. It
would be important to ensure that examples of good operational practice in the
existing structure were not lost in any move to a school-based structure, and
to consider the academic, as well as the financial rationale for the fusion of
smaller cost-centres into larger Schools.
COUN10-P4
KPIs
relating to a number of areas had been updated since the last meeting of
Council, and new KPIs for sport and human resources were presented for the
first time. The following points were noted:
(i)
The
proportion of female professorial staff varied considerably by subject, and the
subject-mix at Loughborough was such that the overall proportion was relatively
low. This was a significant issue for the HE sector as a whole, and the
University was involved in a number of national initiatives.
(ii) A
full analysis of staff diversity, including ethnicity, was undertaken on a
regular basis for Human Resources Committee. It was agreed that this would be
included in the papers for the next meeting of Council. ACTION: Director of Human Resources
(iii) It was agreed
that relevant benchmarks for the KPIs for human resources would be presented in
future reports. ACTION: Director of
Human Resources
07.1 University Budget
2009-10
COUN10-P5
Council RECEIVED an update on
the University’s budget for the current year. A number of adjustments had
been made to the budget considered by Council in November 2009, but the overall
surplus forecast remained at £9.5M.
07.2 Financial Climate
Briefing 2010-2014
Council RECEIVED a
presentation from the Director of Finance on the current and medium-term
financial climate. Council was reminded that in November 2009, it had
considered a Five Year Plan, in support of
the University Strategy Towards 2016. The Plan had
assumed cuts in HEFCE income of 5%, 3%,
and 3% over the following three years, and had indicated that even with
increases in research, advancement and enterprise income, as per the original
Silver Scenario, there would be a need to make savings of £14.7M over
three years (2-3% each year) in order to avoid going into deficit in 2012-13.
Whilst noting the significant uncertainty on which the assumptions contained
within the Plan were based, Council had asked that further work be undertaken
before it was approved for future planning purposes.
Details of HEFCE grant allocations for 2010-11, and associated advice,
had now been published. HEFCE had taken steps to minimise reductions in the
core teaching grant, and the University’s allocation had been increased
by 1.2% (against a predicted cut of 5%). However, this still represented a real
terms cut, taking into account anticipated inflation. The situation beyond
2010-11 remained highly uncertain but indications from HEFCE and the Department
for Business Innovation and Skills were that there would be further significant
cuts in HE funding. The University’s medium-term forecast, requiring
savings over the next three years as described above, was therefore still
relevant.
The
importance of the Value for Money (VFM) agenda in making the best use of
available resources, and operating in the most efficient manner possible was
underlined. A number of VFM ideas had been identified so far by the Executive
Leadership Team, and the Services Working Together and Simplicity agendas were
highlighted. There were a range of other options for reducing expenditure
including ‘salami slice’ savings across all support services and
departments (although targeted differential savings were viewed as being
preferable), and reducing/delaying the capital programme (although this would
impact on the University’s ability to achieve its strategy, for limited
benefit to recurrent funds). Losing a section of activity would be considered
only as a last resort. There were also options for increasing income, for
example from increased international student recruitment, and commercial
activities. However, while these would have a role in addressing the financial
gap, they would not provide a full solution. A number of uncertainties
remained, relating to factors such as tuition fees and associated bursaries,
research funding, pensions, and the possibility of a new government in May
2010.
Unlike
many institutions, Loughborough was starting
from a sound financial position. The University had time, therefore, to establish a project
structure to allow it to meet the financial challenges that lay ahead, while
still delivering on its vision and strategy ‘Towards 2016.’
The
following points were noted in discussion:
(i) Operations
Committee and ELT were in the initial stages of considering the potential for
differential savings targets for separate departments/sections.
(ii) There were
challenges associated with the creation of a cost-saving culture amongst all
staff. However, there had already been a successful engagement with staff as
part of the ongoing “It’s Better Off” campaign to save energy
and reduce the University’s carbon footprint. The renegotiation of the
University’s contracts with its gas and electricity suppliers had also
produced significant savings in this area. Further, the Vice-Chancellor and
Director of Finance would shortly be presenting a series of open-sessions for
all staff on the financial climate, in which they would promote the VFM agenda,
and warn against complacency. It was important that all HoDs, HoSSs, and
members of Council helped to promote a cost-saving culture.
(iii) There would
be strong competition for research funding in the difficult financial climate
that lay ahead, but the University was well placed in terms of its expertise to
benefit from a number of forthcoming initiatives.
(iv) For
demographic reasons, a greater than normal proportion of staff would be
retiring in the next few years. It was likely that this would bring some
staff-cost savings in the short term, but it would be important to maintain the
calibre of academic staff through new appointments.
07.3 HEFCE Recurrent Grant
2010-11
Council RECEIVED a verbal
report from the Director of Finance on the HEFCE recurrent grant for the
academic year 2010-11. The University’s grant allocation had been
increased by 1.2%, which was a more favourable outcome than the 5% cut that had
been anticipated. However, it still represented a real terms cut, given
expectations on inflation. Grants for the majority of the sector had seen
changes in the range -1% to +2.5% before penalties for over recruitment. It was
unlikely that HEFCE would be able to minimise reductions in the core teaching
grant in the next two years to the extent that it had in 2010-11, and it was
realistic, therefore, to expect that Loughborough’s grant would be cut in
real and cash terms in 2011-12 and 2012-13.
COUN10-P6
Council RECEIVED a progress report from the Chief Operating Officer, and NOTED the revised Capital Plan as a framework for making decisions on individual major projects, and action taken by Operations Committee. The following points were noted:
(i) The University had received the HEFCE Consultation on Capital Infrastructure Framework (CIF). This had highlighted carbon reduction and improved space utilisation as key requirements for CIF funding.
(ii) There were two Stage 3 Final Project Approvals:
· Hazlerigg Refurbishment. A cost of £3.875M, slightly below the allocated budget, had been achieved and work had commenced the previous week.
· East Park Design Centre. The cost was £21.604M, 13% less than the allocated budget, and work would begin before the end of March 2010.
09.1 Strategy/Vision for the
Science Enterprise Park
COUN10-P7
Council NOTED a paper describing: (i) the
strategic importance of the Science and Enterprise Park; (ii) the potential
benefits to departments of collaboration with tenants; (iii) the history of
development; and (iv) the successful completion of SportPark in January 2010.
It was noted in
discussion that around 85% of the space in SportPark had already been let.
Smaller tenants were being sought to occupy the remaining space.
09.2 Preferred Developer
COUN10-P8
Council NOTED that significant progress had
been made in the search for a preferred development partner. Final bids were
programmed to be submitted by 7 April 2010, and the Selection Panel would meet
on 27 April 2010 to determine which bid to recommend.
Council APPROVED a proposal to DELEGATE
AUTHORITY to the Chair to sign a contract with the preferred developer, subject
to recommendations from Operations Committee and with the support of the
Enterprise Board and Estates Management Committee. This would allow the
University to meet its commitment to emda, under the terms of the Funding
Agreement, to choose a development partner by the end of May 2010.
Council NOTED that the decision by the Chair
was programmed for 17 May 2010.
Council also APPROVED a proposal to DELEGATE
AUTHORITY for any consequential amendments to the Funding Agreement with emda
that might flow from the development agreement with the developer to Operations
Committee.
A correction to
paper 8 was noted: The last but two sentence on page three should have read:
The recommendation from the Selection Panel will then go to Project Management
Board and also to the members of Estates Management Committee and Enterprise
Board for approval.
8.3
Lease
Surrender – Holywell Park (amended)
COUN10-P9
Council APPROVED:
(i) A recommendation
from the Land Strategy Group to accept the surrender of the lease covering
National Grid Properties (NGrid) Ltd’s interest in the Charnwood Wing of
the Charnwood Building at Holywell Park at a significant premium.
(ii) The
transfer of the unencumbered freehold interest from Germanischer Lloyd
Industries Ltd (GLIS) for a nominalsum.
COUN10-P10
Council NOTED that the University had recently contributed to a sector-wide consultation on proposed changes to the Financial Memorandum and on HEFCE’s new role regulating HEIs as charities. Council’s attention was drawn in particular to changes proposed within the draft Financial Memorandum relating to the inclusion of responsibilities of Governors and Chair of Governors, which had implications for the role and responsibilities of Council members. Many of the proposed new requirements were virtually identical to those contained in existing CUC best practice guidance for governing bodies and would not represent a significant change to existing LU practice. However, many institutions saw aspects of the proposals as a threat to their institutional autonomy and further consultation was likely. Once more details were known, Council would receive a full briefing.
10/11
Audit Committee
11.1 Report
of Meeting – 11 February 2010
COUN10-P11
Council RECEIVED the report from the meeting of the Audit Committee
held on 11 February 2010. It was noted that Audit Committee had received an
analysis of the needs, tender process and timetable for securing internal audit
services from July 2010, and had agreed that in the longer term some
significant changes might be necessary.
11.2 Appointment of Internal
Auditors
Council NOTED
that Audit Committee had agreed to extend the appointment of KPMG as the
University’s Internal Auditors until July 2012.
12.1 Pro-Vice-Chancellor
(Research)
COUN10-P12:
NOTED
12.2 Pro-Vice-Chancellor
(Teaching)
COUN10-P13:
NOTED
12.3 Pro-Vice-Chancellor
(Enterprise)
COUN10-P14:
NOTED
The Chairman reported on the following meetings
which had taken place on 18 March 2010:
(i) Remuneration
Committee had considered issues relating to pay and pensions.
·
The
normal procedures for determining pay levels for senior staff would be
followed, but detailed parameters would not be decided upon until July 2010, by
which time further financial information would have emerged.
·
The
tax system as it related to pensions had become more complex in recent years,
and there would be a communication to highly paid staff in due course on
relevant sources of advice and information.
(ii) Chairman’s
Advisory Group had focused primarily on considering the financial prospects for
the University.
Council RECEIVED a report from the Vice-Chancellor on
the following items:
(i) Recent
Developments at the University
(ii) Policy Developments for HE
in the UK
COUN10-P15
(iii) National
Pay Negotiations
The
following matters were noted in particular:
·
It had been announced on 2 March 2010 that the
AstraZeneca site in Loughborough would close by the end of 2011. This was a
very serious economic blow for Loughborough and the East Midlands as a whole,
as a large number of jobs would be lost to the area, and Council noted its
concern for all residents and staff affected by this decision. The University
was part of an economic task group, and would also carefully monitor
developments for potential impact on the Science and Enterprise Park.
·
The University had responded positively to an
invitation from the Olympic Park Legacy Company to be involved in a feasibility
study relating to the proposed establishment of a centre for higher educational
activity on the 2012 London Olympics site. The proposal offered potential
opportunities for the University to extend its access to the international
student market, to develop partnerships with overseas institutions with similar
interests, and to engage in other activities in the capital. Council would
receive regular updates on progress.
·
The next phase of national pay negotiations was
shortly due to start, and Council AGREED that Loughborough should be
part of the national negotiating process.
COUN10-P16
Council RECEIVED an update
from the Appointment Working Group for the next Chair of
Council. The long list of potential candidates had been reduced to two, and it
was anticipated that the Working Group would shortly be in a position to
recommend an appointment.
16.1 Council APPROVED revisions to the Terms of
Reference of Nominations Committee.
COUN10-P17
16.2 Council APPROVED revisions to role and duties
of the Chancellor.
COUN10-P18
16.3 Council APPROVED the re-appointment of Ric
Parker as a co-opted member of Council until 31 July 2013.
16.4 Council RECEIVED the report from the meeting of
the Nominations Committee held on 26 November 2009.
COUN10-P19
COUN10-P20 & COUN10-P21
(This item was unstarred to receive tabled paper
COUN10-P21). Council RECEIVED the
reports from the meetings held on 27 January and 3 March 2010, and:
17.1 APPROVED Programme Proposals.
17.2 APPROVED the establishment of the Design Research School.
COUN10-P22
Council
APPROVED amendments to the
constitution of the Health, Safety and Environmental Committee to remove the
post of Pro-Vice-Chancellor from
the membership of the Committee.
COUN10-P23
COUN10-P24
Council RECEIVED the
Radiation Protection Officer’s Annual Report.
Council RECEIVED reports from the following Committees:
21.1 Advancement Committee
– 10 February 2010 [COUN10-P25]
21.2 Enterprise Board
– 9 December 2009 & 10 February 2010 [COUN10-P26]
21.3 Estates Management
Committee – 5 November & 14 December 2009 [COUN10-P27]
21.4 Health, Safety and
Environmental Committee – 17 February 2010 [COUN10-P28]
21.5 Performance Monitoring
Group – 19 November and 1 December 2009 [COUN10-P29]
21.6 Student Experience
Committee – 18 November 2009
& 24 February 2010 [COUN10-P30]
21.7 Costing and Pricing
Committee – 13 January 2010 [COUN10-P31]
10/22 Date of Next Meeting
Thursday, 8 July 2010 (1.30pm)
Author – Chris Dunbobbin
Date – April 2010
Copyright (c) Loughborough University.
All rights reserved.